The new schedule monitoring method combines CC/BM with activity cruciality.
We incorporate activity duration uncertainty into the project expediting process.
It can easily monitor schedule deviations and quickly respond by taking actions.
The introduction of activity cruciality greatly reduces the control effort.
A variable action threshold relating to dynamic project performance is better.