摘要
2006年9月发现大亚湾核电站2号机组换料水箱底板底部有微量水渗出。本工作通过地震分析、应力计算、断裂力学分析,对发现渗漏的大亚湾核电站2号机组换料水箱进行分析与评估。
The evaluation of leak of the refueling water storage tank bottom plate for Daya Bay Nuclear Power Station was finished by the seismic analysis,stress analysis and crack analysis.
引文
[1]THOMAS W M.Evaluation of the refuelingwater storage tank bottom plate crack[R].[S.l.]:[s.n.],2000.
[2]EPRI.Evaluation of flaw in austenitic steel pip-ing,NP-4690-SR[R].[S.l.]:[s.n.],1986.
[3]RCC-M 2000版及2002补遗[S].[出版地不详]:[出版者不详],2000.
[4]ASME规范Ⅺ[S].[出版地不详]:[出版者不详],2004.